15-Year District Facilities Master Plan
DISTRICT FACILITIES MASTER PLAN
In 2013, the District's 15-Year Facilities Master Plan was created. At that time, approximately $240 million worth of work was identified that needed to be completed throughout District 66 in the coming years.
PHASE I: In May 2014, Phase I of the Facilities Master Plan was approved by our voters for $79.9 million worth of work that focused on safety and security throughout all buildings and campuses, and included new buildings for Sunset Hills, Oakdale, Swanson, and Prairie Lane. All four buildings serve as tremendous sources of pride for their neighborhoods. Extensive remodeling work was done at Westside Middle School as well. All projects were done ON TIME and ON BUDGET! Click Here for details of Phase I.
PHASE II: On May 9, 2023, district voters approved a $121 million bond for Phase II that included new buildings for Hillside, Westgate and Loveland, as well as facility updates and upgrades at Paddock Road, Rockbrook, Westbrook, Westside Middle School, Westside High School, Underwood Hills and the District ABC Building.
Click Here to view the Phase II Design and Construction Schedule.
Click Here for more detailed information on Phase II projects currently underway.
NEW WESTGATE ELEMENTARY SCHOOL
- Originally built in 1956 and then rebuilt hastily in Summer 1975 after the May 1975 tornado
- $23 million project expanded the school from 49,979 square ft to 54,515 square ft.
- Completed on time and under budget and opened in December 2025
NEW LOVELAND ELEMENTARY SCHOOL
- Originally built in 1932
- New facility construction began in June 2026, with a projected cost of $24 million
- Square footage of new school will expand from 34,524 square ft to 54,515 square ft
- Part of the original 1932 structure is being preserved and will serve as the new media center
- Project is estimated to be complete in December 2027
NEW HILLSIDE ELEMENTARY SCHOOL
- Originally built in 1954
- $27 million project expanded the school from 56,267 square ft to 64,682 square ft
- Completed ahead of schedule and under budget and opened in November 2025
WESTSIDE MIDDLE SCHOOL
- Underwent a major renovation and expansion of the cafeteria as part of a $5 million project in 2025
- Bright and spacious and inviting with many flexible seating options
- Serves as a wonderful space for community events
WESTSIDE HIGH SCHOOL
- Underwent extensive remodel and expansion work between March 2024 and August 2026
- Over $14 million was used to greatly enhance and expand the cafeteria by 3,000 square feet, increasing seating capacity from 384 to 624
- Locker rooms, as well as restrooms throughout the building, were renovated
- Major mechanical, electrical, and plumbing issues were addressed
ROCKBROOK ELEMENTARY SCHOOL
- A $3.5 million addition that includes a new early childhood center and brand new gymnasium
- The new gym serves as a community storm shelter
- Opened in August 2026
PADDOCK ROAD ELEMENTARY SCHOOL
- A $3.5 million addition that includes a new early childhood center and brand new gymnasium
- The new gym serves as a community storm shelter
- Opened in August 2026
WESTBROOK ELEMENTARY SCHOOL
- During the summers of 2025 through 2028, approximately $10 million of work is being completed that includes:
- new windows, concrete, and pavement repairs
- repairs and improvements to address ADA accessibility issues
- infrastructure repairs and enhancements to lighting, electrical, mechanical, and plumbing systems
ABC DISTRICT OFFICE
- A $2.5 million project - completed in December 2025 - that addressed multiple mechanical and ADA accessibility issues
- An elevator was installed, and the Student Services Welcome Center and district boardroom were expanded and renovated
UNDERWOOD HILLS EARLY CHILDHOOD CENTER
- Approximately $9 million was spent between 2024 and 2026 to address electrical and mechanical issues
- Carpeting, paint and other infrastructure needs were also addressed
LOOKING AHEAD FROM 2026 through 2031
The district will continue to address facility needs in a proactive manner. In the summer of 2027, we will greatly enhance our Performing Arts Center at Westside Middle School with new lighting and sound. A new, larger performance stage will replace the current smaller stage. Also in the summer of 2027, we will be investing in the Westside MIddle School track and field with a new artificial turf field, a new track with jump pits, new grandstand seating, new lighting, and new concession and restroom buildings.
The district continues to allocate money annually to maintain and improve our facilities, and to ensure well-maintained and well-groomed green spaces and landscaping on all district campuses. We will further address HVAC needs at Westside High School, and continue to explore parking solutions at WHS.